Which statement best describes what happens during the Construction phase in Agile?

The team focuses only on programming

The team finalizes all documentation

The team iterates to develop a market-ready solution

The team collaborates to produce a usable increment

In Agile, the Construction phase is characterized by a collaborative effort among team members to produce a usable increment of the product. This phase emphasizes teamwork and communication, allowing members to work closely together, incorporating feedback and adapting to changes along the way. The goal during Construction is not just to code but to create a working version of the product that can be demonstrated to stakeholders.

This approach aligns with Agile principles, which prioritize working software and customer collaboration over extensive documentation or rigid processes. By focusing on collaboration and producing a usable increment, the team ensures that they are meeting customer needs and can make necessary adjustments based on stakeholder feedback.

The other options do not fully capture the essence of the Construction phase. While programming is a vital part of the process, it is not the only focus; documentation is important but not finalized during this phase as Agile favors just-in-time documentation; and while iterating to a market-ready solution is important, it lacks the emphasis on collaboration that is central to Agile practices.